#LESNERBRIDGE update from Project Manager – “Wind is the other constraint that we have in operating the gantry crane and it cannot be operated when the wind is gusting above 30 MPH….”

February 9th 2016 update:

Lesner Bridge Aficionados and Engineering Observers:

Through the freezing temperatures, the mixture of rain, snow and sleet, and the blustery winds blowing off the Bay that make this a true winter garden spot in the South – and with Christmas Eve with temps in the 80’s a distant memory – crews have persevered and continued to move along on the Lesner Bridge Replacement project. Exactly how and what is better explained by the project manager and a favorite of bridge groupies everywhere – Chris Wojtowicz.

So, to be really informed, keep scrolling down and read the informative update that Chris has supplied us while freezing his . . . cheeks off . . . . on the bridge project site.

Feel free to let Chris or me know if you have any questions or need more information. If you haven’t had the opportunity to watch this construction sequence animation, please check it out: https://www.youtube.com/watch?v=fVkeFJWm85s&feature=youtu.be

As a reminder, we are regularly updating information on our WEB page at: http://www.vbgov.com/lesner-bridge. You can also follow us on Twitter at: @lesnerbridge.

If you know of someone who would like to be added to our update list, please have them get in touch with me at this e-mail address and I will be glad to add them. Please feel free to pass this along to others.

Thanks again for all of your interest and patience throughout this project. Please be careful during these icy times and if you happen to be riding by the site and see Chris freezing out there, stop and pet him on the head and give him something hot to drink. He’ll be your friend for life!

Stay warm!

Drew Lankford
Media and Communications
Department of Public Works
City of Virginia Beach

dlankfor@vbgov.com
(O) 757.385.8062
(C) 757.409.4353

****************************************************************

Folks:

As winter begins to remake its cold presence felt, the bridge contractor is about to reach mid-span of the new westbound Lesner Bridge. But before we discuss the upcoming work, I want to mention what has been completed since the December update:

Ø Span 3 (of 10) of the new westbound Lesner Bridge was completed in early January 2016;

Ø The gantry crane has been launched to span 4 and is currently being loaded with the pre-cast concrete segments for span 4;

Ø The footings and columns for piers 5 and 6 have been completed;

Ø The footing for pier 7 has been completed;

Ø We completed segment casting for spans 5 and 6;

Ø The 36-inch storm drain that crossed Cape Henry Drive in the area located just east of Bubba’s Restaurant was installed;

Ø The mechanically stabilized earth (MSE) wall located along the former Duck Inn property was completed; and

Ø We completed conduit and duct installation on the east side of the bridge behind Abutment B.

Completed Spans 1, 2, and 3 of the new Westbound Lesner Bridge

Completed Spans 1, 2, and 3 of the new Westbound Lesner Bridge

The wet, cool, and windy weather is slowing our progress since we need the mating surfaces of the concrete segments to be dry and at or above 40° F in order for us to apply the water sealing epoxy prior to joining the segments together.

Wind is the other constraint that we have in operating the gantry crane and it cannot be operated when the wind is gusting above 30 MPH. Winter work next to Chesapeake Bay and over Lynnhaven Inlet has been a challenge for us these last several weeks. Span 4 of the new westbound bridge was scheduled to be completed by 1/20/2016, but the various winter weather events and the upcoming cold and windy forecast have caused that schedule to slip at least until 2/19/2016. Considering this current delay, the new westbound bridge is now expected to be complete by August 2016, and the traffic switch moved to the new bridge sometime in September 2016. The contractor is now making Saturdays and some Sundays regular work days in an effort to make up some of this lost schedule.

Completed Column and Footing for Piers 4 (background), 5 (formwork still attached), and 6 (foreground)

Completed Column and Footing for Piers 4 (background), 5 (formwork still attached), and 6 (foreground)

Although critical construction work has slowed on the bridge superstructure, other non-critical work on the bridge substructure continues. The steel reinforcement for pier column 7 has been tied is being readied for placement on the recently completed footing. The column formwork has been removed from pier column 5 and will be moved to pier 7 to form up the new column.

At the same time, all of the epoxy coating on the completed footing at pier 9 has been applied and all of the shoring removed and re-installed at pier 8. Excavation for the footing at pier 8 continues and will be completed this week. By 2/12/2016, we expect to have the column for pier 7 fully formed and the footing for pier 8 excavated, the drilled shaft foundations cut down to plan elevations, and footing formwork installed.

Typical segments being positioned at Pier Column 4

Typical segments being positioned at Pier Column 4

We are also aware of several potholes that have formed on the east side of the bridge along the westbound lanes between the bridge and Page Avenue. We expect to have them filled before the end of the week. Many of you have also phoned and emailed about our construction camera being down. For a variety of reasons, this camera has been offline more often than not. The camera is working now and we hope that we have corrected the operating issues.

We have also installed a second camera on the east side of the inlet to better document our work as the bridge construction continues to progress to the east side of the inlet. This second camera is available from the same internet link as the original one provided at http://www.vbgov.com/lesner-bridge.com If this link does not work, please try http://www.workzonecam.com/projects/rshcs Thank you all for alerting us to this issue.

Utility conduits being installed inside the westbound Lesner Bridge

Utility conduits being installed inside the westbound Lesner Bridge

Utility installation inside the completed bridge spans has also begun. This work will continue and will be timed such that as the last span of the bridge is completed, the internal utility installation will also be near completion. This work is critical in relocating the various utilities from the existing bridges to the new westbound bridge within an acceptable timeframe so as to not delay the start of the old bridge demolition and new eastbound bridge construction.

AMI, Inc. in Portsmouth, continues to build the new westbound bridge segments. A total of 115 of the 168 bridge segments have been cast.

**A word of driver caution: As we deliver the segments to the project site or to the gantry, Virginia Beach Police will temporarily stop traffic at the Shore Drive/East Stratford Street Intersection for a few minutes to assist the segment delivery trucks in safely crossing this intersection. These deliveries are not on a set schedule, but will generally occur between the hours of 9:00 AM and 3:00 pm M-F and on some Saturdays, so please be careful as you approach this intersection.**

Over the next two weeks, the bridge contractor will:

Ø Deliver and load the gantry with the remaining span 4 bridge segments

Ø Install the temporary post-tensioning bars and epoxy the span 4 segments

Ø Install and post-tension the permanent tendons through the bridge segments in span 4 of 10 of the westbound bridge

Ø Form and place the concrete in the column for Pier #7

Ø Form and place the concrete in the footing for Pier #8

Ø Install various utilities inside the completed sections of the westbound bridge

Ø Install the new storm drain structures along East Stratford Street on the north side of Shore Drive.

That’s it for now. Please drive safely!

– Chris

Christopher J. Wojtowicz, PE
Project Manager
City of Virginia Beach
Department of Public Works
Engineering Division
2405 Courthouse Drive
Virginia Beach, VA 23456-9031
Office: (757) 385-5785
Fax: (757) 385-5668
Email: cwojtowi@vbgov.com

” City staff are exploring the idea of building a new City Hall at Town Center, potentially through a public-private partnership, as they research what to do with their aging municipal headquarters. “

SouthsideDaily.com:

An inter-office memorandum prepared Friday by Public Works Director Phil Davenport at City Manager Dave Hansen’s request produced a rough estimate of $48.6 million to design and construct a 140,000-square-foot City Hall at Town Center. Alternatively, the city could have a private firm design, construct and own the building, and lease it back to the city at a cost of about $3.99 million annually, according to the memo.

” Charlie’s Seafood Restaurant, one of the last surviving old-school Virginia Beach fish houses, will close on Valentine’s Day, according to the owners. “

Article at Pilotonline.com:

Not much has changed in the 70 years since it opened. Cooks use the same saute pans and pots seasoned with years of use. In the dining room, the floor is covered by the same cream-and-red checkered tiles. Rows of chrome-and-red Formica tables fill the pinewood-paneled dining room.

   
 

Baylines Newsletter of the City Council-appointed Bayfront Advisory Commission February edition

View Baylines Newsletter (4pg PDF):

Marina Shores development proposed
Developers of a proposed 261-unit , four-story apartment complex on the site of the Marina Shores marina along Long Creek made a presentation to the Bayfront Advisory Commission at its last meeting. . . .

Bayfront projects starting soon
Two new Public Works projects are coming to the Bayfront area, beginning this spring. The Greenwell Road Sidewalk Project . . .Shore Drive Bike Facility . . .

Election deadline looms
The deadline to register, change address or name for the March 1 Presidential Primary elections in Virginia Beach is the close of business, Monday, Feb. 8 . . .

Upcoming events
 The Parks and Recreation Department has identified 19 possible sites for installing bicycle racks at beach access entrances. . . .

The Joint Expeditionary Base – Fort Story will hold a public festival on the base to mark its 100th Anniversary Saturday, May 21, from 10 a.m, to 4 p.m. . . .

Be sure to check out all the scoop in Baylines.

From Tour de Virginia Beach July 2009 advocating for more bike lanes.

From Tour de Virginia Beach July 2009 advocating for more bike lanes.

“That message a couple of years ago marked the humble beginning of what’s shaping up as one of the boldest public works proposals in recent Virginia history.”

Read more at Pilotonline.com:

What Henifin has in mind is turning the treated wastewater into something useful. He wants to make it so clean that you and I could safely drink it, and then he wants to inject it more than a thousand feet underground into an aquifer that’s being rapidly depleted.

In doing so, he hopes to address a bunch of problems vexing coastal Virginia.