#LESNERBRIDGE update from Project Manager – “The dredging of Crab Creek and the area in front of the temporary wharf at the Lynnhaven Dredge Material Storage Site (LDMSS) continues today, but will be complete by tomorrow, 2/28/2015.”

February 28th 2015 update:

Is anybody ready for spring? The Lesner Bridge project team is!

The recent spate of snow, ice, and cold has had a negative impact on the project schedule which we hope to make up once the weather warms up. This doesn’t mean that that all work has stopped though.

The dredging of Crab Creek and the area in front of the temporary wharf at the Lynnhaven Dredge Material Storage Site (LDMSS) continues today, but will be complete by tomorrow, 2/28/2015.

image001-2

Ø Construction of the retaining wall along the entire length of the new eastern bridge approach (former Duck Inn property) continues and is about 50% complete;

Ø The foundation for the new traffic signal pole at located at the corner of Page Avenue and Shore drive was installed;

Ø Pier column #1 for the new WB bridge has been completed;

Ø The foundations for bridge piers 2 and 3 have been completed;

Ø The reinforcing steel for Pier column #2 has been tied and is ready for placement on the completed foundation;

Ø The contractor is preparing material for the temporary cofferdam to be built around the foundation for water Pier #3

Ø Equipment and material have been mobilized to bridge pier #4 and the temporary equipment trestle is nearing completion in preparation for installed of the foundation shafts;

Ø Four more bridge segments have been built at the casting yard which brings us past the halfway mark for Span #1 (there are 10 spans per bridge);

image002-2
Over the next two weeks, work will continue on the east side of the bridge as we continue to build the retaining wall, and install storm drain/other utilities. Drilled shaft installation for the foundations at pier #4 will resume on Monday, 3/2/2015. Also next week we anticipate standing the rebar cage for Pier #2 and begin the formwork installation in preparation for placement of the concrete. The installation of the foundation for the new traffic signal pole at the corner of Vista Circle and Shore Drive (across the street from Starbucks) is also expected to take place next week..

That about wraps it up for now. Stay warm, stay dry, and drive safely!

-Chris

Christopher J. Wojtowicz, P.E.
Project Manager
City of Virginia Beach
Department of Public Works
Municipal Center-Bldg 2
2405 Court House Drive
Virginia Beach, VA 23456-9031
Phone: (757) 385-5785
Fax: (757) 385-5668
email: cwojtowi@vbgov.com

Screen grab of construction cam shot taken on Feb 26th 2015 2am

Screen grab of construction cam shot taken on Feb 26th 2015 2am

Discuss

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s