“BOTH EASTBOUND AND WESTBOUND TRAFFIC CROSSING THE BRIDGE WILL BE REDUCED TO A SINGLE LANE IN EACH DIRECTION.” Saturday 10am to 10pm #LesnerBridge Update.

PLEASE SHARE ENTHUSIASTICALLY !

Expect delays caused by single lane in both directions from 10am to 10pm.

From an email update from Project Manager:

Folks:

In the last project update (11/22/2017) we mentioned that we had issues with one of the 10 drilled shaft foundations for Pier #5 of the new eastbound bridge. Between the holidays, cold weather, and a longer than expected duration for remediation of drilled shaft #1 at Pier #5 construction of the EB bridge superstructure had been temporarily suspended. That was the bad news.

Now the good news. Shaft #1 at Pier #5 has been fully remediated, all 10 drilled shafts in this footing have been cut down to the correct elevation, and all of the reinforcing steel for the footing has been placed. The footing is now ready to receive the 400 cubic yards of concrete which is planned for tomorrow, February 3rd, 2018. The concrete will be delivered to this footing via two concrete pumper trucks parked near the center span of the Lesner Bridge eastbound lanes.

This, unfortunately, means lane closures on Lesner Bridge for most of the day tomorrow, Saturday February 3, 2018. Here are the details:

Beginning tomorrow, 2/3/2018 at approximately 10:00 AM single lane closures will be setup on Shore Drive approaching eastbound Lesner Bridge between DuPont Circle and Vista Circle. Single lane closures will also be setup during this time for westbound Shore Drive traffic approaching Lesner Bridge between Page Avenue and East Stratford Street. BOTH EASTBOUND AND WESTBOUND TRAFFIC CROSSING THE BRIDGE WILL BE REDUCED TO A SINGLE LANE IN EACH DIRECTION. BOTH eastbound lanes on Lesner Bridge will be CLOSED until the concrete placement operations are completed. All work and temporary lane closures on Shore Drive at Lesner Bridge are expected to be cleared by 10:00 PM Saturday night, February 3rd, 2018. Be advised that, in addition to the lane reductions on the bridge, there will also be flaggers present that will intermittently STOP all traffic in BOTH directions on the bridge to allow the arrival and departure of concrete delivery trucks.

There will be a lot of activity on the bridge tomorrow so please plan accordingly and drive slowly when crossing the bridge.

Once Pier #5 is complete, we will launch the gantry across the inlet, set the pier segments on Pier #5 and then launch to Pier #6 and set the pier segments on Pier column #6. Span #6 will then be assembled by picking segments off a barge moored in this location. After Span #6 is completed, the gantry will be back-launched toward the channel to complete the other half of the cantilever section of Span #5 that crosses the channel.

Footing Reinforcing Steel being placed at Pier #5 EB Bridge (Completed Pier Column #6 shown in background)

View looking East from East Stratford Street at the recently graded area for the 10-foot wide multi-use path that will cross the new EB Bridge.

Since the last update other work on the project continued while waiting for Pier #5 to be completed. The following work has been completed since the November 22, 2017 update:

· 4 additional segments of cantilever Span #5 have been constructed for the new EB bridge (8 total);

· The footing and column at Pier #7 have been completed;

· The cofferdam around the footing for Pier #8 has been installed and the and the area around the drilled shafts excavated;

· All four drilled shafts at Pier #9 have been installed (ALL DRILLED SHAFT INSTALLATION FOR THE PROJECT IS NOW COMPLETE);

· Abutment B for the EB bridge has been completed;

· Grading for the new 10-foot wide multi-use path between the new EB Bridge and East Stratford Street has been completed;

· The remaining two street lights (four total) on the western bridge approach have been installed;

Completed Abutment B EB Bridge. Forms being removed.

Completed Footing and Column at Pier #7 new EB Bridge (Forms shown being removed).

Over the next two weeks, the bridge contractor will:

· Complete the footing and column at Pier #5;

· Place reinforcement steel for the footing at Pier #8;

· Backfill Abutment B and complete MSE wall #5 located in front of the Virginia and Maryland Pilots Association;

· Install falsework for gantry launch at Pier #5;

· Complete concrete multi-use path along MSE wall #2 between East Stratford and the new EB Bridge; and

· Complete curb & gutter and median curb on the west side of the bridge between East Stratford Street and the new EB Bridge.

That’s it for now!

Drive Safely!

-Chris

Christopher J. Wojtowicz, PE
Engineering Construction Manager
City of Virginia Beach
Department of Public Works
Engineering Division
2405 Courthouse Drive
Virginia Beach, VA 23456-9031
Office: (757) 385-5785
Fax: (757) 385-5668
Email: cwojtowi@vbgov.com

2 thoughts on ““BOTH EASTBOUND AND WESTBOUND TRAFFIC CROSSING THE BRIDGE WILL BE REDUCED TO A SINGLE LANE IN EACH DIRECTION.” Saturday 10am to 10pm #LesnerBridge Update.

Discuss

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s