Milling and Paving Started – Shore Drive Between Greenwell Rd and Lesner Bridge

Virginia Beach Public Works has announced that crews began roadway improvements on Shore Drive beginning Sunday, August 11, 2019.

The project will include milling, paving and pavement marking improvements which will begin on Shore Drive, both eastbound and westbound lanes, from Greenwell Road to the Lesner Bridge

Crews will be working beginning at 7 p.m. and will end at 5 a.m. each day.

The project is expected to be completed by Friday, September 20, 2019.

The milling and paving operation is likely to produce traffic delays, congestion and some construction noise. Advanced warning signs will be clearly posted advising motorists of lane closures. Citizens are urged to use alternate traffic routes when possible.

All scheduled work is weather permitting.

Virginia Paving is the contractor for the project. For additional information, please contact Lonnie Minson with Virginia Paving at (757) 675-8714, or Dennis Simon at (757) 385-1470.

To read the official City news release, click here Shore Drive – Greenwell to Lesner – August 2019

DISCUSS

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.